Ithaca, N.Y. — Construction firm Welliver has been busy craning the new steel atrium trusses into place, with at least four installed when these photos were taken the weekend before last.
My laymen’s mind would call the shape almond-like or a pinched oval, but Wikipedia tells me the proper terms are “vesica piscis” or “mandorla”, both of which sound like alien species doing battle with Captain Kirk.
One of the site cranes has completed its work and has been removed, while the other will stay in place until all the structural steel has been erected.
On the lower floors, fireproofing, mechanical and electrical rough-in (plumbing and wiring) is underway, while concrete pouring is taking place in parts of the upper levels.
Some of this work would be visible from the fences, were it not for the plastic sheeting put up to keep the frigid winds at bay.
Over the month of February, construction schedules indicate that fireproofing will wrap up on the south side of the ground level, leading the way for sheetrock installation and exterior and interior wall framing.
At the same time, fireproofing will begin on the north side of the ground level, and concrete will continue to be poured for the auditorium space and upper levels.
The 33,250 sq ft building was designed by Koetter | Kim & Associates, and is due to open in December 2015. Construction cost is estimated at $61 million.
Here are some photos from the recent visit: